NEW QUESTION # 27
What is the purpose of the Daily Scrum? Select two answers
- A. Inspect the increment
- B. Receive directions from the Product Owner
- C. Adapt the Sprint Backlog as necessary
- D. Inspect progress toward the Sprint Goal
- E. Report progress and status
- F. Adapt the Product Backlog
Answer: C,D
NEW QUESTION # 28
What are the Key value areas? Select all answers that apply
- A. Ability to innovate
- B. Unrealized Value
- C. Current Value
- D. Time to Market
- E. Realized Value
- F. Previous Value
Answer: A,B,C,D
NEW QUESTION # 29
You manage a development organization. One of your Scrum Teams is continually interrupted by unplanned work related to production incidents for a legacy application unrelated to their product. A few team members have historical knowledge of the legacy application. How should the Scrum Team manage the interruption and unplanned work? (choose the best answer)
- A. New development work should be put on hold until the production support work is completed; supporting existing applications is always more important than new work.
- B. Work with the Scrum Team to help transfer the knowledge to other teams better aligned with the application support mission.
- C. The Scrum Team should fit the work in, working overtime if that is what it takes.
Answer: B
Explanation:
In Agile, protecting the Scrum Team's focus is important. Transferring knowledge to the appropriate teams ensures that the team can focus on its current product development without being interrupted by unrelated work. This approach aligns with the principle of minimizing distractions and maintaining focus on delivering value.
NEW QUESTION # 30
What is the Ability to Innovate?
- A. The organization's ability to quickly deliver new capabilities, services, or products
- B. The innovation provided by the Product
- C. The potential future value that could be realized if the organization met the needs of all potential customers or users
- D. The value of innovation
- E. The effectiveness of an organization to deliver new capabilities that might better meet customer needs
- F. The value that the product delivers today
Answer: E
NEW QUESTION # 31
When a Scrum Team fails to deliver a working product Increment for several Sprints in a row, who is accountable for resolving this situation?
(Choose the best answer)
- A. The Project Manager.
- B. The Developers.
- C. The Scrum Team.
- D. The Team Lead.
- E. The Product Owner.
- F. All the above.
Answer: C
Explanation:
Scrum is built on the principle of self-managing teams, meaning that accountability for delivering a working product Increment lies with the entire Scrum Team-not just individual roles.
According to the Scrum Guide (2020):
The Scrum Team is responsible for delivering valuable, high-quality Increments.
The Developers are responsible for creating a "Done" Increment in each Sprint.
The Product Owner ensures the Product Backlog is clear, prioritized, and aligned with business needs.
The Scrum Master helps remove impediments, coach the team, and facilitate continuous improvement.
There is no "Team Lead" or "Project Manager" role in Scrum, as leadership is distributed within the Scrum Team.
Analysis of Each Answer Option:
#Option A: The Developers.
Developers are responsible for building the Increment, but they do not operate in isolation.
The failure to deliver working software could stem from issues in backlog prioritization, impediments, or ineffective team collaboration-areas that involve the entire Scrum Team.
#Option B: The Product Owner.
The Product Owner defines and prioritizes work, but they do not control how it gets delivered.
While the Product Owner plays a key role in ensuring backlog items are clear and valuable, they alone cannot fix delivery issues.
#Option C: The Team Lead.
Scrum does not recognize a "Team Lead" role-leadership is shared across the Scrum Team.
In self-managing teams, all members take ownership of quality and delivery, rather than relying on a single leader.
#Option D: The Project Manager.
Scrum does not include the role of a Project Manager.
In Agile environments, planning, execution, and accountability are handled within the Scrum Team, rather than by an external project manager.
#Option E: The Scrum Team. (Best Answer)
Scrum Teams are collectively accountable for delivering working Increments.
They must inspect and adapt-leveraging Sprint Retrospectives and collaborative problem-solving to improve delivery.
The Scrum Master facilitates improvement efforts, the Product Owner refines priorities, and the Developers address technical challenges-making it a shared responsibility.
#Option F: All the above.
Incorrect because not all listed roles exist in Scrum (e.g., Project Manager, Team Lead).
Only the Scrum Team as a whole is accountable.
References from Professional Agile Leadership (PAL) Documents:
Scrum Guide (2020) - The Scrum Team is accountable for creating a valuable Increment every Sprint.
Professional Agile Leadership Essentials (PAL-E) Guide - Agile leaders support teams in being self- managing, rather than assigning accountability to individual roles.
The Agile Manifesto - Principles Behind the Agile Manifesto - Encourages collaboration, continuous improvement, and shared ownership.
Empirical Process Control in Scrum - Encourages inspection, adaptation, and transparency to improve delivery.
By applying these Scrum principles, Option E is the best answer, as the Scrum Team collectively owns the responsibility for resolving delivery challenges.
NEW QUESTION # 32
What is Product Backlog refinement?
- A. The act of breaking down and further defining Product Backlog items into smaller more precise items.
- B. The time that the Product Owner reserves to write requirements.
- C. The Scrum event where Product Backlog items are broken down into smaller more precise items.
Answer: A
NEW QUESTION # 33
Which of the following statements are true about Technical Debt? Select two answers.
- A. Only the Developers need to be concerned with Technical debt.
- B. Technical debt is a threat to the long-term viability and maintainability of a product.
- C. A team that continuously incurs technical debt will increase the velocity in the short term. Changes and development will seem easy and fast.
- D. Technical debt can be handled after delivery with refactoring sprints.
- E. The amount of technical debt is described as quality standards in the Definition of Done.
Answer: B,C
NEW QUESTION # 34
Where may you add the most impactful improvements of the retrospective?
- A. To the Product Backlog
- B. to the Scrum board
- C. To the Sprint Backlog for the next Sprint
- D. to the Impediments backlog
- E. to the task board
- F. to the Release backlog
Answer: C
NEW QUESTION # 35
A new agile initiative is being mobilized, and you are the manager tasked with staffing the teams. How do you decide which team each member should belong to? (choose the best answer)
- A. Group people together who have a similar skill set to maximize efficiency and utilization.
- B. Bring together interested people, discuss product goals, remind teams that they need to balance skills and experience, and let the teams self-organize.
- C. Group people together who already know each other from previous teams.
- D. Assign people to teams in such a way that balances skills, experience, and seniority as evenly as possible.
- E. Group people together based on which components of the system they are most familiar with.
Answer: B
Explanation:
Agile encourages self-organizing teams, where individuals collaborate to determine how to best achieve their goals. This approach leverages the collective skills and experience of the team and fosters a sense of ownership and accountability. Letting teams self-organize also aligns with Agile's emphasis on autonomy and empowerment.
NEW QUESTION # 36
Which of the following Key Value Measures (KVMs) would be useful to understand and improve the Time-to-Market? Select three answers
- A. Time to remove Impediment
- B. Customer Satisfaction
- C. Ability to Innovate
- D. Change Failure Rate
- E. Time to Pivot
- F. Time-to-Learn
Answer: A,E,F
NEW QUESTION # 37
You are an Agile Leader working with five Scrum Teams. One of the Scrum Team requires a new working environment to replicate the production environment and help the team perform security and performance testing. The strict company policies allow creating new environments only for actual production purposes and not for any testing. Security and performance testing are needed as part of the Team's Definition of Done before the completed work can be shippable.
How would you manage this situation? Select two possible answers.
- A. Work with the Scrum Team to see how they can do the testing in their existing development environment. They should try to replicate the production environment as much as possible.
- B. Ask the Scrum Team to come up with alternate solutions to resolve this issue themselves. You will support them as needed.
- C. Support the needs of the team. Work with the senior management to get the environment approved.
- D. Extend the Sprint to focus on security and performance testing.
- E. Remove security and performance testing from the Definition of Done.
Answer: A,B
NEW QUESTION # 38
You are interviewing a candidate to work as a Scrum Master in your company, you ask the candidate to briefly explain "Scrum".
Which of the following responses would you expect? Select four answers.
- A. Scrum is an agile method that can only be used to develop software.
- B. Scrum is a lightweight framework that helps people, teams and organizations generate value through adaptive solutions for complex problems.
- C. Scrum is a collection is of best practices for building products.
- D. Scrum is founded on lean thinking.
- E. Different processes, techniques and methods can be employed within the framework.
- F. Scrum is founded on empiricism.
Answer: B,D,E,F
NEW QUESTION # 39
A member of a Scrum Team is interested in understanding the organization's ability to deliver value. She asks if he can explain what the Time to Market Key Value Area (T2M) can reveal.
What would you answer?
- A. The organization's ability to quickly deliver new capabilities, services, or products
- B. How quickly the organization can develop Products.
- C. The average time required to perform a release.
- D. The average velocity across all Scrum Teams in the organization.
Answer: A
NEW QUESTION # 40
During a management meeting, a Manager reports that he is having issues getting one of his teams to take ownership of the project. The team always escalates decisions to him and asks him for directions.
What would you advise him to do?
- A. Explain to them that they must be self-directed and they must take ownership and decisions.
- B. Meet the team members and work with the team to understand their expectations and impediments to take decisions. Coach them about becoming self-managing.
- C. At Sprint Planning, assign a different person each sprint as the decision-maker to get them all comfortable in the role.
- D. Congratulate team members that take decisions and report the lack of participation to the functional managers.
Answer: B
NEW QUESTION # 41
Which of the following KVMs provides insight into the capacity of the organization to deliver new product capabilities?
- A. Customer Cycle Time
- B. Technical Debt
- C. Installed Version Index
- D. Innovation Rate
- E. On-Product Index
- F. Release Frequency
Answer: D
NEW QUESTION # 42
Measures usually fall into activities, outputs, and outcomes
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION # 43
The Sprint Backlog can be updated throughout the Sprint
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION # 44
What describes the single objective of the Sprint?
- A. Increment Goal
- B. Definition of Done
- C. Sprint Goal
- D. Business Goal
- E. Product Goal
- F. Company Goal
Answer: C