Use the best ways of preparing for AACE-PSP Exam Dumps with DumpTorrent AACE International AACE-PSP dump PDF [2022]
AACE International AACE-PSP exam candidates will surely pass the Exam if they consider the AACE-PSP dumps learning material presented by DumpTorrent.
NEW QUESTION 66
Resource planning must take all of the following into account except for
- A. Time available to complete the project.
- B. Earned value techniques established for the project.
- C. Cash flow (expenditure) limitations for completing work on the project.
- D. Types of materials, equipment and labor skills required to complete the project.
Answer: B
NEW QUESTION 67
Total float is defined as the amount of time an activity can be delayed without impacting
- A. The buoyancy of a successor activity
- B. The end of that activity
- C. The next activity
- D. The overall project completion
Answer: D
NEW QUESTION 68
By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:
- A. Acceleration.
- B. Production output.
- C. Productivity efficiency.
- D. Productivity loss.
Answer: D
NEW QUESTION 69
Determine the correct formula and date for the late finish for Activity 2002.
- A. LS.2003 - 1 day -> 11.06.01.
- B. LS.2003 + 1 day -> 10-07-01.
- C. LS.2003 - 1 day -> 10-06-01.
- D. LS.2003 - 1 day -> 10-05-01.
Answer: D
NEW QUESTION 70
What owner action could have mitigated the late completion of the project?
- A. Hire a more senior project manager.
- B. Self-perform more of the work.
- C. Prepare better structural steel drawings.
- D. Use a procurement agent to monitor and expedite equipment deliveries.
Answer: D
NEW QUESTION 71
Why does activity 11001 not show successor activities?
- A. It is the final activity for the required work for the project
- B. The early finish and late finish are circular
- C. The scheduler forgot to add the successor activities
- D. It is the penultimate work required for the project
Answer: A
NEW QUESTION 72
Estimate to complete (ETC) is __________________.
- A. The costs actually incurred in accomplishing the work performed
- B. The value of the completed work expressed in terms of the budget assigned to that work
- C. The expected remaining cost needed to complete an activity, group of activities or the project
- D. The expected total cost of an activity, group of activities or the project
Answer: C
NEW QUESTION 73
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?
- A. 150 lifts
- B. 450 lifts
- C. 300 lifts
- D. 45 lifts
Answer: B
NEW QUESTION 74
Activity C is a
- A. Continuous activity.
- B. Contentious activity.
- C. 1-day activity.
- D. Milestone.
Answer: D
NEW QUESTION 75
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
- A. Accuracy is increased by inserting delaying events into the as-planned schedule.
- B. Less accurate as the analysis advances through the project.
- C. Not suitable for projects with long durations.
- D. Not suitable for complicated projects with multiple planned critical paths.
Answer: A
NEW QUESTION 76
What is the relationship depicted between Activity G and Activity H?
- A. Finish-to-start.
- B. Start-to-start.
- C. You cannot tell with the supplied information.
- D. Finish-to-finish.
Answer: B
NEW QUESTION 77
Under which circumstance should one perform resource-leveling calculations?
- A. When the contract contains a provision for float-banking.
- B. Never, unless required by the contract.
- C. When the schedule is resource-loaded.
- D. When you believe that known resource limitations may override schedule logic.
Answer: D
NEW QUESTION 78
Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?
- A. Entering the time impacts of delays and change orders.
- B. Estimating remaining durations of activities.
- C. The correct recording of actual start dates.
- D. Making "downstream" logic revisions as required.
Answer: D
NEW QUESTION 79
In its simplest form, what is the main drawback of critical path method scheduling?
- A. It doesn't account for interdependent between activities.
- B. It assumes that resources are unlimited.
- C. It requires a backward pass to calculate late dates.
- D. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.
Answer: B
NEW QUESTION 80
The linear scheduling velocity diagram has the following two-axis:
- A. Location and crew size
- B. Time and crew size
- C. Time and rate of progress
- D. Time and location
Answer: C
NEW QUESTION 81
What is the free float for Activity F?
- A. 3 months.
- B. 1months.
- C. 2month.
- D. 0months.
Answer: D
NEW QUESTION 82
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?
- A. 18 work days
- B. 7 work days
- C. 8 work days
- D. 15 workdays
Answer: C
NEW QUESTION 83
What was the original planned duration for Activity A through Activity G?
- A. 26.
- B. 24.
- C. 25.
- D. 28.
Answer: D
NEW QUESTION 84
At the end of month one, did the delay to the parking structure foundation delay the project?
- A. Yes, by 9 calendar days.
- B. Yes, by 14 calendar days.
- C. NO.
- D. Yes, by 4 calendar days.
Answer: D
NEW QUESTION 85
......
Full AACE-PSP Practice Test and 120 unique questions with explanations waiting just for you, get it now: https://drive.google.com/open?id=1SRZaRpMffR-F8ydZlgYwU4pyJTFvoWRS
Accurate & Verified Answers As Seen in the Real Exam here: https://www.dumptorrent.com/AACE-PSP-braindumps-torrent.html